Mercier Bridge 132 ramp and lane closures
11/06/2015
The Mohawk Council of Kahnawà:ke (MCK) has been informed by the Jacques Cartier and Champlain Bridges Incorporated that each direction of the Route 132 ramp will be completely closed this weekend on the following schedule:
- Saturday, November 7th from 2am-10am: o La Prairie-bound downramp completely closed
- Sunday, November 8th from 2am-10am: o Montreal-bound upramp completely closed
These ramp closures are required to carry out cleaning work on the expansion joints. Detours will be clearly marked for each ramp closure.
Furthermore, the Ministère des Transports du Quebec will close the left lane of Route 132 East (towards Montreal) on Monday, November 9th from 9am until 12 noon to allow work on the median.
The MCK reminds the public that these works are subject to change due to weather conditions, operational constraints or work progression, and that it does not take part in the scheduling or cancellation of such works.
|